PRINCE2 page types#

PRINCE2 index#

Lists the project’s management products and their state.

Project Mandate#

The client’s instruction that starts the project: the need and the outcome wanted. Not how or when.

Project Brief#

Defines the project from the Mandate: objectives, scope, constraints, tolerances, users, outline business case, project product and approach.

Project Initiation Documentation (PID)#

The baseline for running the project: links the definition, Business Case, roles, approaches (quality, risk, issue, communication), plan, controls and tailoring.

Business Case#

Why the project is worth doing: reasons, options, benefits, dis-benefits, timescale, costs and major risks. Reviewed at each gate.

Organisation and roles#

Who holds each PRINCE2 role and whether it is confirmed.

Communication Management Approach#

Who receives what, through which channel and how often.

Project Plan#

Stages, dated schedule with dependencies, critical path, assumptions and the cost table.

Stage Plan#

The current stage in detail and the next stage in outline.

Product Breakdown Structure and Product Descriptions#

The products the project must deliver, and for each: purpose, composition, derivation, format, quality criteria, quality method and responsibilities.

Work Packages#

Agreed parcels of work: products, owner, dates, tolerances, dependencies and acceptance.

Registers#

Risk, issue, quality, daily log, lessons and decisions, each with a unique ID and status. Records are closed, never deleted.

Change Control#

Log of change requests with impact and decision, and the blank request form.

Configuration Item Records#

The controlled items (management products and EV pages), their status, location and owner.

Highlight Report#

Periodic report to the Executive: status, work done, work next, tolerances, changes, issues, risks, lessons.

Report templates#

Blank Checkpoint, Exception and End Stage Reports in PRINCE2 7 composition.